STATE OF
INDIANA |
) |
|
BEFORE THE
INDIANA DEPARTMENT |
||
|
|||||
COMMISSIONER
OF THE DEPARTMENT Complainant, v. INTAT
PRECISION, INC., Respondent. |
) |
|
|||
AGREED
ORDER
Complainant
and Respondent desire to settle and compromise this action without hearing or
adjudication of any issue of fact or law, and consent to the entry of the
following Findings of Fact and Order.
Pursuant to IC 13-30-3-3, entry into the terms of this Agreed Order does
not constitute an admission of any violation contained herein. Respondent's entry into this Agreed Order
shall not constitute a waiver of any defense, legal or equitable, which
Respondent may have in any future administrative or judicial proceeding, except
a proceeding to enforce this order.
I. FINDINGS OF FACT
1.
Complainant is the Commissioner (“Complainant”)
of the Indiana Department of Environmental Management (“IDEM”), a department of
the State of Indiana created by Indiana Code (“IC”) 13-13-1-1.
2.
Respondent is INTAT Precision, Inc.
(“Respondent”), which owns and operates a stationary gray and ductile iron
foundry with Plant I.D. No. 139-00011 located at 2148 State Road 3 North in
Rushville, Rush County, Indiana (the “Site”).
3.
IDEM has jurisdiction over the parties and the
subject matter of this action.
4.
Pursuant to IC 13-30-3-3, IDEM issued a Notice
of Violation (“NOV”) via Certified Mail to:
Tomiyuki Murayama, President |
The
Prentice-Hall Corporation System Inc., |
INTAT
Precision, Inc. |
Registered
Agent |
2148
N. State Road 3 |
135
N. Pennsylvania St, Suite 1610 |
Rushville,
IN 46173 |
Indianapolis,
IN 46204 |
5.
During an investigation conducted by a
representative of IDEM, the following violation was found:
Pursuant to Part 70 Permit
139-38971-00011, issued to Respondent on November 21, 2017, condition
D.4.8(a)(4), and corresponding conditions in subsequent permits require, PM, PM10,
PM2.5, and Lead testing for the baghouse DC-N2 (Stack S-N2)
controlling the following Line 4 operations: Pouring and Cooling (EU-N3 and
EU-N4), Casting Shakeout (EU-N5) Bad Heat Shakeout (EU-N5A), Shot Blast Unit
(EU-N6), and Sand Cooler. This test shall be conducted not later than sixty
(60) days after the new Shot Blast Unit (EU-N6) achieves maximum capacity but
no later than one hundred-eighty (180) days after initial startup of the new
Shot Blast Unit (EU-N6).
Respondent failed to conduct stack testing not later than sixty (60) days after
the new Shot Blast Unit (EU-N6) achieves maximum capacity but no later than one
hundred-eighty (180) days after initial startup of the new Shot Blast Unit
(EU-N6), in violation of Part 70 Permit 139-38971-00011 condition D.4.8(a)(4),
and corresponding conditions in subsequent permits.
6.
Respondent conducted stack testing for the
baghouse DC-N2 (Stack S-N2) on February 21, 2018.
7.
In recognition of the settlement reached, Respondent
waives any right to administrative and judicial review of this Agreed Order.
II. ORDER
1.
This Agreed Order shall be effective
(“Effective Date”) when it is approved by Complainant or Complainant’s
delegate, and has been received by Respondent.
This Agreed Order shall have no force or effect until the Effective
Date.
2.
Respondent shall comply with Part 70 Permit
139-38996-00011, unless superseded by a permit modification or renewal.
3.
All submittals required by this Agreed Order,
unless Respondent is notified otherwise in writing by IDEM, shall be sent to:
Matthew Chaifetz, Compliance and
Enforcement Manager |
Compliance and Enforcement Branch –
Mail Code 61-53 |
Indiana Department of Environmental
Management |
100 North Senate Avenue |
Indianapolis, IN 46204-2251 |
4.
Respondent is assessed and agrees to pay a
civil penalty of Seventeen Thousand One Hundred Eighty-Seven Dollars and Fifty
Cents ($17,187.50). Said penalty amount
shall be due and payable to the Environmental Management Special Fund within thirty
(30) days of the Effective Date; the 30th day being the “Due Date”.
5.
Civil penalties are payable by check to the
“Environmental Management Special Fund.” Checks shall include the Case Number of this
action and shall be mailed to:
IDEM
Office of Legal Counsel |
IGCN,
Rm N1307 |
100
N Senate Ave |
Indianapolis,
IN 46204 |
6.
This Agreed Order shall apply to and be binding
upon Respondent and its successors and assigns. Respondent’s signatories to this Agreed Order
certify that they are fully authorized to execute this Agreed Order and legally
bind the party they represent. No change
in ownership, corporate, or partnership status of Respondent shall in any way
alter its status or responsibilities under this Agreed Order.
7.
In the event that the monies due to IDEM
pursuant to this Agreed Order are not paid on or before their Due Date,
Respondent shall pay interest on the unpaid balance at the rate established by
IC 24-4.6-1. The interest shall be
computed as having accrued from the Due Date until the date that Respondent
pays any unpaid balance. Such interest
shall be payable to the Environmental Management Special Fund, and shall be
payable to IDEM in the manner specified in Paragraph 5, above.
8.
In the event that any terms of this Agreed
Order are found to be invalid, the remaining terms shall remain in full force
and effect and shall be construed and enforced as if this Agreed Order did not
contain the invalid terms.
9.
Respondent shall provide a copy of this Agreed
Order, if in force, to any subsequent owners or successors before ownership
rights are transferred. Respondent shall
ensure that all contractors, firms and other persons performing work under this
Agreed Order comply with the terms of this Agreed Order.
10.
This Agreed Order is not and shall not be
interpreted to be a permit or a modification of an existing permit. This Agreed Order, and IDEM’s review or
approval of any submittal made by Respondent pursuant to this Agreed Order,
shall not in any way relieve Respondent of its obligation to comply with the
requirements of its applicable permit or any applicable Federal or State law or
regulation.
11.
Complainant does not, by its approval of this
Agreed Order, warrant or aver in any manner that Respondent’s compliance with
any aspect of this Agreed Order will result in compliance with the provisions
of any permit, order, or any applicable Federal or State law or
regulation. Additionally, IDEM or anyone
acting on its behalf shall not be held liable for any costs or penalties
Respondent may incur as a result of Respondent’s efforts to comply with this
Agreed Order.
12.
Nothing in this Agreed Order shall prevent or
limit IDEM’s rights to obtain penalties or injunctive relief under any
applicable Federal or State law or regulation, except that IDEM may not, and
hereby waives its right to, seek additional civil penalties for the same
violations specified in the NOV.
13.
Nothing in this Agreed Order shall prevent IDEM
or anyone acting on its behalf from communicating with the EPA or any other
agency or entity about any matters relating to this enforcement action. IDEM or anyone acting on its behalf shall not
be held liable for any costs or penalties Respondent may incur as a result of
such communications with the EPA or any other agency or entity.
14.
This Agreed Order shall remain in effect until
IDEM issues a Resolution of Case letter to Respondent.
TECHNICAL
RECOMMENDATION: |
|
RESPONDENT: |
|||||
Department
of Environmental Management |
|
INTAT Precision, Inc. |
|||||
|
|
|
|||||
By: |
|
|
By: |
|
|||
|
David
P. McIver, Chief |
|
Printed: |
|
|||
|
Enforcement
Section |
|
Title: |
|
|||
|
Office
of Air Quality |
|
|
|
|||
Date: |
|
|
Date: |
|
|||
|
|
|
|
|
|||
|
|
|
|||||
|
|
COUNSEL
FOR RESPONDENT: |
|||||
|
|
|
|||||
|
|
|
|||||
|
|
|
By: |
|
|||
|
|
|
|
|
|||
|
|
|
|
|
|||
|
|
|
Date: |
|
|||
|
|
|
|
|
|||
APPROVED
AND ADOPTED BY THE INDIANA DEPARTMENT OF ENVIRONMENTAL |
|||||||
MANAGEMENT THIS |
|
DAY OF |
|
,
2019. |
|||
|
|||||||
|
For
the Commissioner |
||||||
|
|
||||||
|
Signed
on June 14, 2019 |
||||||
|
Matthew
Stuckey, Deputy Assistant Commissioner |
||||||
|
Office
of Air Quality |
||||||
|
Indiana
Department of Environmental Management |
||||||