CADDNAR
[CITE: DCG Services, et al.
v. DNR, 15 CADDNAR 54 (2019)]
[VOLUME 15, PAGE 54]
Cause #: 13-156W
Caption: DCG Services, et al. v. DNR
Administrative Law Judge:
Jensen
Attorneys: Tucker-Young
(DCG); Gamboa (DNR)
Date: March 20, 2019
[See Editor’s
note at end of this document regarding change in the decision’s original format.]
Final Order
- The NOV issued by the
Department is hereby affirmed in all respects
except to the extent the Petitioners were alleged to have filled the
stream channel of Sulphur Creek.
- The Petitioners shall mitigate
the violations affirmed by this Order by conducting activities as
specified by and within the time frames provided by the Department in the
NOV’s section entitled “Action Appropriate to Mitigate the Violation”.
- The Petitioners shall
pay the assessed $5,000 civil penalty within thirty (30)
days after the opportunity for judicial review, or subsequent
appeal, has expired.
- Failure to comply with
the mitigation requirements, as set forth in the NOV and ordered in
Finding 79, shall result in the imposition of additional civil penalties
as set forth in the NOV’s section entitled “Civil Penalty
Assessment”.
FINDINGS OF FACT AND CONCLUSIONS OF LAW WITH FINAL ORDER
Procedural Background and Jurisdiction
- For consideration in this
proceeding is a Notice of Violation, identified as VTS-5505-FW,
(hereafter referred to as “the NOV”) issued by the Respondent,
Department of Natural Resources (Department), to DCG Services,
Inc., Abydel Farms, LLC, John M. Divine, Linda
M. Divine, and George R. Ziegler, on August 22, 2013.
- The
NOV alleges that the individuals to whom it was issued violated Indiana
Code §§ 14-28, commonly referred to as the Flood Control Act, or FCA, by engaging in “excavation within the channel of
Sulphur Creek, excavation of tree stumps and roots within the floodway,
fill placement within the floodway, and filling of the existing stream
channel” without having first obtained “prior written approval” of the
Department through its Division of Water. The Department maintained
that the NOV was issued as an enforcement action authorized by Indiana
Code §§ 14-25.5.
- The NOV assessed a civil
penalty in the amount of $5,000 with further
notice that additional penalties would accrue following a failure to take
corrective action as specified within the NOV.
- On September 13, 2013,
DCG Services, Inc., Abydel Farms, LLC, John M.
Divine and Linda M. Divine (hereafter referred to collectively as “the
Petitioners”), by counsel, Jennifer Tucker Young, timely filed, with
the Natural Resources Commission (Commission), their request for
appeal or administrative review under Indiana Code § 4-21.5-3-6.
- George R. Ziegler (Ziegler)
did not seek administrative review or otherwise appeal the Department’s
issuance of the NOV. Further, Ziegler did not intervene in the
instant action commenced by the Petitioners. Testimony
of Ziegler.
- The Department and the
Commission are the administrative agencies responsible for the
administration of the FCA. Indiana Code
§§ 14-28.
- The Administrative
Orders and Procedures Act, commonly referred to as AOPA,
is applicable to Indiana Code §§ 14-28 and 14-25.5. Indiana Code §§ 14-28-1-30 and 14-25.5-2-4.
- The Indiana General
Assembly established a “legislative design” for the Department and the
Commission by which the “Director of the
[Department] would receive all day-to-day decision-making authority.
Departmental decisions would be appealed through the administrative
adjudication process, with the Commission acting as final adjudicative
authority.” Juday Creek, et al. v. Ralph Williams and Associates and DNR,
8 CADDNAR 90, 92 (1998).
- With respect to actions
of the Department under the FCA and Indiana Code
§§ 14-25.5, the Commission serves as the “ultimate authority”. Indiana Code §§ 4-21.5-1-15 and 14-10-2-3.
- The Commission possesses
jurisdiction over the subject matter of this proceeding and of the persons
of the parties.
- Administrative Law Judge
(ALJ) Jensen was appointed in accordance
with Indiana Code § 14-10-2-2 on September 18, 2013.
- ALJ Jensen conducted a
Prehearing Conference on October 17, 2013. The record of the instant
proceeding indicates that settlement discussions were ongoing between
October 17, 2013 and April 1, 2016. On October 5, 2017, the
Department sought to have the instant proceeding scheduled for a
telephonic Status Conference, which was granted.
Since the Status Conference, conducted on November 1, 2017, the parties
have engaged in additional settlement discussions, participated in
additional Status Conferences on January 17, May 30, and June 20, 2018;
conducted discovery, exchanged witness and
exhibit lists. Ultimately, the parties participated in an
Administrative Hearing conducted on August 28, 2018.
- The parties timely filed
Post Hearing Briefs on September 28, 2018.
- Pursuant to Indiana Code
§ 4-21.5-3-14(d), administrative review is conducted de novo.
Findings of Fact
- The real property at
issue in the NOV is owned by individual Petitioner, Abydel
Farms, LLC, having been conveyed by Warranty Deed executed by individual
Petitioners, John M. Divine (Divine) and Linda M. Divine, on
December 27, 2012. Testimony of Divine;
Respondent’s Exhibits 8 & 9; Petitioners’ Exhibit B.
- Jon Eggen
(Eggen), is the manager of the
Department’s Division of Water Compliance and Enforcement Section. Eggen conducted a property record search for the
property at issue in the NOV. Testimony of Eggen. He agreed that the real
property is owned by individual Petitioner, Abydel
Farms, LLC. Eggen’s
testimony that the principals for Abydel Farms
LLC, are individual Petitioners, John M. Divine
and Linda M. Divine, was not contested and is deemed conclusory. Testimony of Eggen.
Evidence that individual Petitioner, DCG Services, Inc., was, at the time of issuing the NOV, identified as the
Registered Agent for Abydel Farms, LLC, was also
not contested and is considered accurate. Id.
- Suzanne Delay (Delay)
is a Registered Professional Engineer in the State of Indiana working in
the Compliance and Enforcement Section of the Department’s Division of
Water. Delay holds a degree in Agricultural Engineering from Purdue
University and continues to engage in required continuing education.
Delay has been employed with the Department for 23 years in various
sections of the Division of Water conducting permit
reviews,
preparing floodway/floodplain determinations and fulfilling other
responsibilities. Testimony of Delay.
[VOLUME 15, PAGE 55]
- Delay explained the
process of using HEC-RAS computing software,
which is generally accepted for use in defining the limits of a floodway
using available data from varying sources, including watershed and
drainage area information, FEMA Flood Insurance Rate Mapping, and land
elevation topographical mapping. With respect to the real property
at issue in the NOV she was tasked with preparing
a floodway determination. Id.
- Delay prepared a
floodway determination for the area along Sulphur Creek that includes the
real property owned by Abydel Farms, LLC that is
at issue in the NOV. Testimony of Delay,
Respondent’s Exhibits 8 & 9. No evidence was presented to contradict Delay’s floodway
determination and it is accepted as accurate.
- Master Conservation Officer
Anthony W. Mann (Mann) who had been employed
by the Department’s Law Enforcement Division for 27 years at the time of
the Administrative Hearing has been assigned to Martin County for 21
years. As particularly relevant to the instant proceeding
Mann’s responsibilities as a Master Conservation Officer include the
enforcement of the laws of the State of Indiana and the Department of
Natural Resources.
- On April 6, 2013, Mann
was notified by dispatch to investigate a complaint that Divine was “‘digging
in the creek’ above Indian Springs”, which activity was causing the water
to be “cloudy and unsuitable” at a
distance downstream of the activity location. Testimony of Mann, Respondent’s Exhibit 27.
- Mann identified the
location of the activity to be “at Sulphur Creek …just off of Cale Road in Martin County.”
Upon arrival, Mann observed Ziegler operating a track hoe, or excavator, digging
in Sulphur Creek. He also observed what he recognized to be field tile installation equipment being operated by
Divine in the near vicinity. Testimony of Mann.
- Mann observed Ziegler
using the track hoe to remove silt, otherwise referred to in testimony as
a sandbar, from a curve in Sulphur Creek. Id. Mann
elaborated that excavation was occurring within the channel of Sulphur
Creek, stating explicitly “he was literally scooping out the silt of the
creek.”
- Mann testified that he
observed Ziegler depositing the silt removed from the channel along the
banks of the channel “just within the reach of the track hoe; he wasn’t
removing it from the floodway.”
- Ziegler told Mann that
he was conducting the activities in Sulphur Creek at the direction of
Divine. Testimony of Mann. On
April 6, 2013, Ziegler had removed approximately six beaver dams using the
track hoe before Mann arrived and he had conducted similar activities on
at least two prior occasions at the request of Divine. Testimony of Ziegler. Ziegler’s testimony was not disputed.
- Piles of trees debris
and woody vegetation existed on the sides of Sulphur Creek. Testimony of Adams, Respondent’s Exhibits 11 & 13.
Adams and Eggen testified that some of the trees
had been cut while other trees had been removed
by excavating the roots. The Petitioners did not dispute Eggen’s testimony that the root balls from fully
excavate trees were in locations on the north side of the railroad tracks
where he presumed trees and roots were removed to create tillable land
where farming is ongoing in 2018. Divine countered that the tree debris and woody vegetation had been left in piles by the
logging company that he hired to harvest trees from the property.
Testimony of Divine.
Divine’s testimony proves he was aware of the existence of piles of tree
debris and woody vegetation.
- The Petitioners offered
no evidence in opposition to Adams’ testimony that the piles of tree
debris and woody vegetation were not secured in
any way.
- Beaver activity can
result in significant damage, which may be to crops or in the form of
chewed off trees. Particularly beavers’ construction of dams across
waterways can cause or worsen flooding. Testimony
of Mann & Ziegler. Mann did not observe beaver chewed
trees in the vicinity, however, it is reasonably concluded from the
evidence that standing trees had been removed from the area near Sulphur
Creek by the timber harvest authorized by Divine while the piles of tree
debris and other woody vegetation offered a readily available supply of
material for constructing beaver dams.
- Mann acknowledged that
the water level in Sulphur Creek on April 6, 2013 was above the outlet of
the existing field tile, which would have prevented the field from
draining. Testimony of Mann & Divine.
- Mann contacted Toby
Adams (Adams) regarding the complaint lodged against the
Petitioners. Adams, an Environmental Manager in
the Division of Water, has been employed by the Department for 20 years.
His responsibilities include conducting inspections in conjunction with
the Department’s obligations to ensure compliance with and enforcement of
the FCA in the southern portion of
Indiana. Adams holds a degree in Environmental Science from Indiana
University’s School of Environmental Affairs.
- The Petitioners did not
have a permit authorizing the activities that had and were continuing to
occur on the real property specified in the NOV. Testimony
of Mann & Adams.
- Adams, alone, conducted
an inspection of the site on April 13, 2013 and was joined
by Delay and Eggen in conducting a second
subsequent inspection on April 30, 2013. Adams has inspected the
site at issue in the NOV on multiple occasions since April 30, 2013.
- Despite Divine’s
testimony that no excavation was conducted, the
evidence presented by the Department supports the conclusion that
excavation had occurred in the channel of Sulphur Creek. “Spoil
piles” of material removed from the creek channel had been dumped along
the banks in a manner consistent with what Mann testified to having
observed on April 6, 2013. The spoil piles were void of any
vegetation indicating to Adams that the piles had only
recently been created. Testimony of
Adams, Delay & Eggen; Respondent’s Exhibits
14 & 15. The creek bed was no longer smooth as if
shaped by the flow of water, but instead, photographic evidence revealed
the appearance of square shaped depressions consistent with the bucket of
a track hoe. Testimony of Delay, Respondent’s
Exhibit 15.
- Adams testified that in
“one or two locations where the stream meandered in a large pattern…it was excavated across that meander and it was cut off…”
thereby altering the watercourse. Respondent’s Exhibit 18.
With respect to the one of these locations for which the Department
introduced specific evidence, Divine testified that water flow had been diverted because beaver had constructed a dam
across the meander. While no beaver dam remained in the area of the
diversion when Adams was present in April 2013, Adams acknowledged that a
meander could also be cut off by the existence of
a beaver dam. Testimony of Adams.
By cutting off the meander, also referred to in testimony as an oxbow, the
stream is shortened and straightened causing increased water velocity,
which contributes to downstream erosion. This activity interferes
with aquatic plant and animal life in the area deprived of water flow as
well as in areas scoured by increased water velocity. Testimony of Adams.
- Eggen acknowledged
uncertainty with respect to the NOVs allegation
that the Petitioners had engaged in placing fill in the channel of Sulphur
Creek.
- The evidence is not
sufficient to establish whether the Petitioners or beaver dams were
responsible for the particular diversion of water discussed in Finding 34
as depicted in Respondent’s Exhibit 18.
- Aerial photographs
obtained from Google Earth were compared to
understand the “history of the site” from a pictorial perspective.
Railroad tracks are evident running in an east/west direction across the
center of the photograph. In the bottom right corner, or southeast
corner, of the photo Cale Road is depicted as a curving or winding road traveling in a
general south-east/north-west direction. Sulphur Creek, is visible
to the
south of
the railroad tracks meandering from the left, or west, side of the photo to the
right, or east, to a point slightly beyond the middle of the photo where
Sulphur Creek turns to run in a north-westerly direction, crossing the railroad
tracks, and running generally parallel to Cale
Road. Respondent’s Exhibits 5 & 6,
Testimony of Adams.
[VOLUME 15, PAGE 56]
- Between 2008 and 2013
all vegetation existing between the south side of the railroad tracks and
the southern-most reaches of the meanders of Sulphur Creek had been removed. Also removed was
all vegetation existing in a sizeable area north of the railroad tracks
bounded by Cale Road to the west and an
agricultural field to the north. Id.
- By
overlaying the floodway determination map prepared by Delay over the 2013 aerial
photograph (an enlarged version of which was identified as Respondent’s
Exhibit 6), it is evident that, with the exception of a small portion of
land located north of the railroad tracks near the center of the photo,
the real property at issue in the NOV, where excavation and clearing
activities occurred, is located within the floodway. Respondents’
Exhibit 9.
- The Department did not
contradict Divine’s assertion that he has been farming part of the
property at issue in the NOV since 1977 and during that entire time he has conducted ongoing maintenance of Sulphur
Creek. Testimony of Divine.
Divine asserted that when Sulphur Creek is blocked by
beaver dams and other obstructions flood waters rise above the railroad
tracks and traverse the field to the west flowing to Little Sulphur Creek
and over the County Road where it floods homes owned by Elton and George Sipes. Id. Divine
was given permission by both George and Elton Sipes
to maintain portions of Sulphur Creek located on property owned by them.
Id.
- Eggen recognized that stream
maintenance such as “trimming trees and brush” may be
conducted without a permit but excavation that disturbs the soil,
as was done by the Petitioners, requires a permit issued by the
Department. Eggen testified, “Beaver dam
removal…they actually come in with a grapple hook and remove the beaver
dam, the woody debris, and remove it completely from the floodway, doesn’t
require a DNR permit. But excavating soil and dredging the stream,
which is what we documented…that does require a
permit.”
- Divine did not explain
the methods he has used since approximately 1977 to maintain Sulphur
Creek.
- The evidence of record
does not indicate whether the Department was aware, until April 2013, of Divine’s
activities to maintain Sulphur Creek.
- Eggen prepared the NOV at
issue in this proceeding, which was signed by the
Department’s Division of Water Director Michael Neyer,
and issued on August 22, 2013. Testimony
of Eggen, Respondent’s Exhibit 19.
- The NOV explains the
nature of the violations for which it was issued
and provides a description of the actions necessary to mitigate the
violation along with time deadlines by which mitigation must be
completed. The NOV also provides information regarding the procedure
by which the Petitioners and Ziegler were able to obtain Administrative
Review. Id. The NOV also imposes an initial civil
penalty of $5,000, with notice that additional penalties would be imposed in the event mitigation activities were
not completed on the specified schedule. Id.
- In the spring of 2018 vegetation had begun to grow in the floodway area
along Sulphur Creek to the south of the railroad tracks but farming was
occurring in the floodway area that had been cleared on north side of the
railroad tracks. Testimony of Adams &
Divine; Petitioners’ Exhibits D through H.
- Adams explained that the
Department’s regulatory control of activities within floodways is to
ensure that activities undertaken by one owner for their own benefit does
not create a surcharge thereby backing up water and causing upstream
flooding or, conversely, that the activity enhances the velocity of waters
to the extent that resulting erosion related damage is significantly
increased downstream.
- Neither Mann, nor Eggen, was familiar with other individuals or entities
the Petitioners inferred or alleged had conducted similar activities to
those alleged in the NOV within Sulphur Creek or other waterways in Martin
County. Testimony of Mann & Eggen. Evidence establishes that the
Department had not issued Notices of Violation to the individuals or
entities identified by the Petitioners. Petitioners’
Exhibit A. While the Petitioners
established that the Department was unfamiliar with and did not issue notices
of violation to the individuals and entities they inferred or alleged to
have engaged in activities in floodways similar to what the Department
alleged in the NOV, the Petitioners failed to provide any evidence that
the Department was aware of activities undertaken by these other
individuals or entities, either by receipt of a complaint or
otherwise. Similarly, the Petitioners failed to provide
specific evidence that the activities engage in by other individuals and
entities were in contravention to the FCA.
- For instance, Jerry Bussinger (Bussinger),
a property owner in Martin County Indiana and neighbor of Divine,
testified that he has never received a Notice of Violation from the
Department. However, Bussinger did not
describe any activity he engaged in within the floodway that may have been
in violation of the FCA such that issuance of a
Notice of Violation by the Department may have been appropriate.
There was also no evidence presented by the Petitioners that the
Department was aware of Bussinger’s activity
within the floodway.
- To
establish that the Department’s issuance of the NOV in this instance as
compared to an alleged failure to act in other similar situations results
from bias or prejudice against the Petitioners so as to support a contention
that the Department’s action was arbitrary, capricious or produced by
unjust motives, it would be necessary to establish (1) that the Department
was aware that other individuals or entities were engaging in the
activity, and (2) that the activity engaged in by the other individuals or
entities were contrary to law. The record is void of such evidence.
Conclusions of Law
- As most appropriately
applicable to the instant proceeding, Indiana Code § 14-28-1-1 declares:
(1) The loss of
lives and property caused by floods and the damage resulting from floods is a
matter of deep concern to Indiana affecting the life, health, and convenience
of the people and the protection of property. To prevent and
limit floods, all flood control works and structures and the alteration of
natural or present watercourses of all rivers and streams in Indiana should be
regulated, supervised, and coordinated in design, construction, and operation
according to sound and accepted engineering practices so as to best control and
minimize the extent of floods and reduce the height and violence of floods.
(2) The channels and
that part of the flood plains of rivers and streams that are the floodways should not be inhabited and should be kept free and clear of
interference or obstructions that will cause any undue restriction of the
capacity of the floodways.
- Throughout the
Administrative Hearing, the Petitioners focused solely upon Section (2) of
Indiana Code § 14-28-1-1, as support for their conclusion that “it is
uncontroverted that Indiana Code 14-28-1, which governs Flood Control,
does not require a permit for routine, ongoing channel maintenance.”
Petitioners’ “Post Hearing Brief”, filed September 28, 2018.
- Indiana Code § 14-28-1-1
must be considered in conjunction with the remainder of the FCA. Prewitt v. State of
Indiana, 878 N.E.2d 184 (Ind.
2007). “To effectuate legislative intent, we read sections of an act
together in order that no part is rendered meaningless if it can be
harmonized with the remainder of the statute.” City
of Carmel v. Steele, 865 N.E.2d 612, 618
(Ind. 2007) citing, Ind. Dep't of Pub. Welfare
v. Payne, 622 N.E.2d
461, 466 (Ind.1993).
- In addition to the
expression of Legislative Intent at Indiana Code § 14-28-1-1, the
Legislature also set forth in relevant part, at Indiana Code §
14-28-1-20(2), that:
Sec. 20. A
person may not do any of the following:
….
(2) … erect, make, use, or maintain in
or on any floodway, or suffer or permit the erection, making, use, or
maintenance in or on any floodway, a structure, an obstruction, a deposit, or
an excavation that will do any of the following:
(A) Adversely affect the efficiency of
or unduly restrict the capacity of the floodway.
(B) By virtue of the nature, design, method of construction, state of maintenance, or physical condition
do any of the following:
(i)
Constitute an unreasonable hazard to the safety of life or property.
(ii) Result in unreasonably
detrimental effects upon the fish, wildlife, or botanical resources.
[VOLUME 15, PAGE 57]
- Further, Indiana Code §
14-28-1-22(c) through (f) offers as follows:
Sec. 22 …
(c) A person who desires to:
(1) erect,
make, use, or maintain a structure, an obstruction, a deposit, or an
excavation; or
(2) suffer or
permit a structure, an obstruction, a deposit, or an excavation to be erected,
made, used, or maintained;
in or on a
floodway must file with the director a verified written application for a
permit accompanied by a nonrefundable minimum fee of two hundred dollars
($200).
(d) The application for a permit must
set forth the material facts together with plans and specifications for the
structure, obstruction, deposit, or excavation.
(e) An applicant must receive a permit
from the director for the work before beginning construction. The director shall
issue a permit only if in the opinion of the director the applicant has clearly
proven that the structure, obstruction, deposit, or excavation will not do any
of the following:
(1) Adversely affect the efficiency of
or unduly restrict the capacity of the floodway.
(2) Constitute an unreasonable hazard
to the safety of life or property.
(3) Result in unreasonably detrimental
effects upon fish, wildlife, or botanical resources.
(f) In deciding whether to issue a
permit under this section, the director shall consider the cumulative effects
of the structure, obstruction, deposit, or excavation. The director may
incorporate in and make a part of an order of authorization conditions and
restrictions that the director considers necessary for the purposes of this
chapter.
- While the concept of
maintaining floodways in a manner unencumbered and unrestricted by
obstructions and other interference is recognized at Indiana Code §
14-28-1-1, the Legislature clearly recognized that some activities carried
out within floodways, including the removal of obstructions by excavation
and the deposit of material, requires regulatory control.
- The Petitioners’
contention that the FCA authorizes the removal
of obstructions from and conducting “ongoing channel maintenance” in floodways,
presumably by any method necessary, including by excavation using a track
hoe, without a permit is inconsistent with the express language of the FCA.
- In fact, the FCA, at Indiana Code § 14-28-1-22(b)(6) expressly
provides, as Eggen noted in his testimony, that;
Sec. 22….
(b)…
(6) The removal of a logjam or mass of
wood debris that has accumulated in a river or stream, subject to the following
conditions:
(A) Work must not be within a salmonid
stream designated under 327 IAC 2-1.5-5 without the prior written approval of
the department's division of fish and wildlife.
(B) Work must not be within a natural,
scenic, or recreational river or stream designated under 312 IAC 7-2.
(C) Except as otherwise provided in Indiana law, free logs or affixed logs that are
crossways in the channel must be cut, relocated, and removed from the
floodplain. Logs may be maintained in the floodplain if properly anchored or
otherwise secured so as to resist flotation or
dislodging by the flow of water and placement in an area that is not a wetland.
Logs must be removed and secured with a minimum of damage to
vegetation.
(D) Isolated or single logs that are embedded, lodged, or rooted in the channel, and that do
not span the channel or cause flow problems, must not be removed unless the
logs are either of the following:
(i)
Associated with or in close proximity to larger obstructions.
(ii) Posing a hazard
to navigation.
(E) A leaning or severely damaged tree
that is in immediate danger of falling into the waterway may be cut and removed
if the tree is associated with or in close proximity to an obstruction. The
root system and stump of the tree must be left in
place.
(F) To the extent practicable, the
construction of access roads must be minimized, and
should not result in the elevation of the floodplain.
(G) To the extent practicable, work should be performed exclusively from one (1) side of a
waterway. Crossing the bed of a waterway is prohibited.
(H) To prevent the flow of sediment laden water back into the waterway, appropriate
sediment control measures must be installed.
(I) Within
fifteen (15) days, all bare and disturbed areas must be revegetated with a
mixture of grasses and legumes. Tall fescue must not be used
under this subdivision, except that low endophyte tall fescue may be used in
the bottom of the waterway and on side slopes.
- A “logjam” was defined
by the Commission to include “an accumulation of lodged trees, root wads,
or other debris that impedes the ordinary flow of water through a
waterway”, evidenced by the fact that it “traverses the waterway”, “causes
upstream ponding”, or results in significant stream bank erosion.” 312 IAC 10-2-26. However,
included in the definition of logjam is the caveat that logjam removal
does not include the removal of resultant sandbars, sedimentation
or accumulations of stone or gravel. Id.
- The NOV issued by the
Department alleges that the Petitioners conducted “unpermitted excavation
within the channel of Sulphur Creek, excavation of tree stumps and roots
within the floodway, fill placement within the floodway, and filling of
the existing stream channel.”
- Evidence is not
sufficient to conclude that the Petitioners engaged in the “filling of the
existing stream channel.”
- The evidence in this
instance that the Petitioners were attempting to remove beaver dams and
other obstructions from Sulphur Creek is accepted
as true.
- Regardless, the
Petitioners’ intent, the Petitioners’ efforts, which included scooping silt
out of the channel of Sulphur Creek with a track hoe, is not consistent
with Indiana Code § 14-28-1-22(b)(6)(C)’s directive to remove the logs
“with a minimum of damage to vegetation.”
- Silt and sedimentation
removal from the channel or from within the floodway of Sulphur Creek
constitutes an excavation in a floodway, specifically from the stream
channel, an activity that required the Petitioners to obtain a
permit. Indiana Code § 14-28-1-22(d).
- The removal of trees
from within a floodway by the excavation of the entire trunk and roots
also constitutes an excavation, which required the Petitioners to obtain a
permit. Id., and Yater v. Department of
Natural Resources, 6 CADDNAR 161, 163
(1994).
- Further, the
installation of field drainage tile being undertaken by Divine on April 6,
2013 as observed by Mann, constitutes excavation
in the floodway requiring a permit from the Department.
- The creation of spoil
piles within the floodway of Sulphur Creek of the silt or sedimentation
removed from Sulphur Creek’s channel constitutes the “deposit” of fill in
the floodway, which required the Petitioners to obtain a permit in
accordance with Indiana Code § 14-28-1-22(d).
- The
evidence established through the Administrative Hearing that tree debris
and woody vegetation removed from the channel of Sulphur Creek by the
Petitioners was deposited in the floodway within the reach of the track
hoe is not consistent with the requirement to remove the logs and tree
debris from the floodplain or secure it “to resist flotation or dislodging
by the flow of water.” Indiana Code § 14-28-1-22(b)(6)(C).
- Because the tree debris
and other woody vegetation was not secured, the
piles of woody vegetation and tree debris are appropriately characterized
as deposits within the floodway the placement of which required a
permit. Indiana Code § 14-28-1-22(d) and Yater, supra.
- The timber company
conducting the timber harvest under authority granted by the Petitioners’
created piles tree debris and woody vegetation within the floodway of
Sulphur Creek. These piles constitute deposits within the floodway,
the occurrence of which requires a permit. Id. While
the timber company may have created the piles of tree debris, the
Petitioners, who are the owner and the principals of the owner of the
property who authorized the timber harvest, were also responsible not to “permit
the erection, making, use, or maintenance in or on any floodway … a
deposit…” Indiana
Code
§14-28-1-20(2). Similarly, Ziegler actually carried out the excavation
of the channel of Sulphur Creek at the direction of Divine, a principal in Abydel Farms, LLC, who permitted and caused
the excavation to occur. Furthermore, the evidence support the conclusion
that Divine was personally involved in excavation activities within the
floodway of Sulphur Creek by engaging in the installation of field drainage
tile within the floodway.
[VOLUME 15, PAGE 58]
- The evidence presented
at the Administrative Hearing established that the channel of Sulphur
Creek was excavated and fill placed in the
floodway by Ziegler at the direction of Divine, who is a principal in Abydel Farms, LLC. The evidence further
established that Divine personally engaged in excavation activities within
the floodway of Sulphur Creek and engaged a timber company that Divine
permitted to create deposits within the floodway. Further, in an
apparent effort to expand the size of its agricultural field, Divine
permitted and caused the removal of trees and excavation of tree roots in
the floodway on the north side of the railroad tracks.
- Indiana Code §
14-25.5-2-2 authorizes the Department to issue a “written notice of
violation if a person violates”, as applicable in this instance, Indiana
Code §§ 14-28.
- The content of the NOV issued
by the Department complies with Indiana Code § 14-25.5-2-3.
- At Indiana Code §
14-28-1-36, the FCA expressly provides that “In
addition to other penalties prescribed by this chapter, the director may
impose a civil penalty under IC 14-25.5-4.” The Department properly
assessed a $5,000 penalty upon the Petitioners and Ziegler.
- In accordance with
Indiana Code § 14-25.5-2-5, the NOV has not become effective as to the
Petitioners because, within 30 days of issuance by the Department, the
Petitioners initiated this proceeding for Administrative Review in
accordance with Indiana Code § 4-21.5-3-6.
- The Department bears the
burden of proving by substantial evidence the facts contained within the
NOV. Yoder v. DNR & Bouwkamp,
12 CADDNAR 88, 100 (2009). The Department has fulfilled this
burden with respect to all the allegations contained within the NOV,
except to the extent the NOV alleges the Petitioners filled a portion of
the stream channel of Sulphur Creek.
- The record is void of
evidence to support the Petitioners’ contention that the Department’s
action in issuing the NOV was biased, arbitrary
or capricious.
[EDITOR’S NOTE: The
original format of the Administrative Law Judge’s Findings of Fact, Conclusions
of Law, and Final Order has been modified to
correspond with CADDNAR format. The Final Order, Paragraphs 78
through 81, has been relocated to the “Final
Order” section at the beginning of this document.]