Article
Superseded and Discontinued Construction Memorandums
Issued |
Subject |
Number |
02/01/24 |
E5 Internal Cure and E5 Liquid Fly Ash in Concrete (rev. 05/15/24) [*Supersedes 23-01* **Superseded by 25-02**] |
24-03 |
01/22/24 |
Infrastructure Investment and Jobs Act - Build America, Buy America [*Discontinued*] |
24-02 |
07/07/23 |
E-Ticketing Incentive [*Discontinued*] |
23-08 |
05/10/23 |
IRI Implementation for CY 2023 [*Supersedes 22-01* **Discontinued**] |
23-04 |
03/13/23 |
E5 Internal Cure and E5 Liquid Fly Ash in Concrete [*Superseded by 24-03*] |
23-01 |
10/26/22 |
Infrastructure Investment and Jobs Act - Build America, Buy America [*Superseded by 24-02*] |
22-09 |
05/12/22 |
Alternate Overlay Mix Design Using E5 Internal Cure and E5 Liquid Fly Ash [*Superseded by 23-01*] |
22-04 |
04/04/22 |
Alternate Curing Method for Structural Concrete using E5 Internal Cure and E5 Liquid Fly Ash [*Superseded by 23-01*] |
22-02 |
03/10/22 |
IRI Implementation for CY 2022 [*Superseded by 23-04*] |
22-01 |
03/18/21 |
21-08 |
|
02/26/21 |
Alternate Curing Method for Structural Concrete Using E5 Internal Cure [*Superseded by 22-02*] |
21-05 |
01/28/21 |
Buy America Certification Supplemental Information [*Superseded by 24-10*] |
21-03 |
01/28/21 |
IRI Implementation for CY 2021 [*Superseded by 22-01*] |
21-02 |
04/17/20 |
Buy America Requirement Clarification Supplemental Instructions [*Superseded by 24-10*] |
20-06 |
04/09/20 |
Submittals and Weigh Tickets During COVID-19 [*Superseded by 21-08*] |
20-05 |
03/16/20 |
QC/QA Hot Mix Asphalt 2020 Specification changes [*Discontinued*] |
20-04 |
03/03/20 |
Buy America Certification [*Superseded by 24-10*] |
20-03 |
01/22/20 |
IRI Pilot Contracts for CY 2020 [*Superseded by 21-02*] |
20-02 |
12/17/19 |
Notice of Termination, NOT [*Superseded by 23-07*] |
19-10 |
06/25/19 |
Modifying IRI Contracts to Utilize the Fixed Interval Method [*Discontinued*] |
19-06 |
02/21/19 |
QC/QA Hot Mix Asphalt 2019 Specification Changes [*Discontinued*] |
19-03 |
02/07/19 |
Implementation of the Electronic Constructability Review Forms (ECRF) [*Superseded by 23-06*] |
19-01 |
11/26/18 |
Determining Construction Equipment Costs [*Superseded by 24-07*] |
18-06 |
06/11/18 |
Maintenance of Impact Attenuator & Guardrail End Treatments [*Superseded by 20-01*] |
18-04 |
01/31/18 |
QC/QA Hot Mix Asphalt Test Strips and Aggregate Gsb Determination [*Discontinued*] |
18-01 |
11/28/17 |
Use of the Law Enforcement Officer for Work Zone Safety [*Superseded by 21-06*] |
17-17 |
11/28/17 |
Change Order Extra Work Cost Verification Procedure [*Superseded by 24-11*] |
17-16 |
11/28/17 |
Revised Item Bid History Spreadsheet for Use with New Items of Extra Work [*Superseded by 24-11*] |
17-15 |
09/20/17 |
LPA and State Shop Drawing and Falsework Review Procedures [*Superseded by 20-10*] |
17-14 |
08/07/17 |
Alternate to Concrete Sealers Unique Special Provision [*Discontinued on 2/1/2018*] |
17-12 |
06/09/17 |
Electronic Payroll Submission by Contractors [*Superseded by 19-07*] |
17-11 |
03/31/17 |
QC/QA Hot Mix Asphalt Test Result Appeals [*Discontinued*] |
17-06 |
03/13/17 |
Buy America Requirement for Utilities [*Discontinued* See Memo 24-10] |
17-04 |
02/22/17 |
Acceptance method for Hot Pour Joint Sealant [*Discontinued*] |
17-02 |
01/19/17 |
Notice of Termination (NOT) [*Superseded by 19-10*] |
17-01 |
10/13/16 |
The New EquipmentWatch Website [*Superseded by 24-07*] |
16-11 |
06/10/16 |
16-06 |
|
06/03/16 |
Implementation of the Contractor Performance Evaluation (CPE) system [*Superseded by 21-10*] |
16-05 |
01/28/16 |
Notice of Termination, NOT [*Discontinued*] |
16-02 |
09/16/15 |
15-16 |
|
08/19/15 |
Binder Deficiency Adjustment [*Discontinued*] |
15-15 |
08/14/15 |
FHWA PY 2016 PODI List for Change Order Approval [*Superseded by 20-11*] |
15-14 |
05/30/14 |
The Removal of FHWA Change Order Approvals from Select Construction Contracts [*Superseded by 15-14*] |
14-07 |
04/22/14 |
Change Orders on Construction Contracts Policy [*Superseded by 22-08*] |
14-05 |
01/30/14 |
Notice of Termination (NOT) [*Superseded by 17-01*] |
14-02 |
11/07/13 |
LPA and State Shop Drawing and Falsework Review Procedures [*Superseded by 17-14*] |
13-13 |
08/30/13 |
N.O.T. Erosion and Sediment Control Inspections and Reports [*Discontinued*] |
13-09 |
07/17/13 |
Transverse Corrugations in Sidewalk Curb Ramps [*Discontinued*] |
13-07 |
05/01/13 |
Notice of Termination (NOT) [*Superseded by 14-02*] |
13-04 |
04/30/12 |
SiteManager Field Enhancement Policies and Procedures [*Superseded by 17-03*] |
12-06 |
03/30/12 |
Non-Participating Pay Items on Change Orders [*Discontinued*] |
12-03 |
12/05/11 |
Payment for Stockpiled Dowel Bar Assemblies [*Discontinued*] |
11-11 |
07/01/11 |
GIFE 2.7.3 Rental ILease Agreements [*Discontinued*] |
11-05 |
03/03/11 |
State and LPA Shop Drawing and Falsework Review Procedures [*Superseded by 13-13*] |
11-02 |
01/31/11 |
Position of Staggered Barricades [*Discontinued*] |
11-01 |
07/02/10 |
Traffic Marking Material Shortages [*Discontinued*] |
10-08 |
06/09/10 |
402 HMA LPA Recovery Act Projects [*Discontinued*] |
10-07 |
02/03/10 |
RAP Binder Replacement Cost Savings Change Orders [*Discontinued*] |
10-02 |
01/04/10 |
New Change Order Policy [*Superseded by 14-05*] |
10-01 |
11/30/09 |
Project Commitments Database [*Superseded by 10-05*] |
09-22 |
11/16/09 |
M-39 & Contract Closeout [*Superseded by 14-03*] |
09-21 |
06/11/09 |
Shop Drawing & Falsework Submittal & Review Procedures for LPA Projects [*Superseded by 11-02*] |
09-13 |
05/06/09 |
Warm Mix Asphalt, WMA [*Discontinued*] |
09-12 |
04/30/09 |
Active Commitments Report [*Superseded by 09-22*] |
09-11 |
04/29/09 |
Overruns on ARRA Contracts [*Superseded by 09-14*] |
09-10 |
03/30/09 |
Construction Zone Impact Attenuators [*Discontinued on 6/5/2015*] |
09-09 |
03/25/09 |
Shop Drawing Submittals for Three-Sided Drainage Structures [*Discontinued on 9/1/2011*] |
09-07 |
02/23/09 |
PCCP Cost Savings Measures [*Discontinued*] |
09-06 |
02/23/09 |
HMA Cost Savings Measures [*Discontinued*] |
09-05 |
02/06/09 |
PG Asphalt Binder Index Material Cost Adjustments [*Discontinued*] |
09-03 |
01/08/09 |
Shop Drawing & Falsework Review Procedures [*Superseded by 11-02*] |
09-01 |
12/02/08 |
Construction Zone Impact Attenuators [*Discontinued on 6/5/2015*] |
08-15 |
08/14/08 |
Payment for Stockpiled Materials (Specification Section 111) [*Discontinued*] |
08-11 |
05/29/08 |
Procedure for How to Handle Existing Construction Claims [*Superseded by 09-16*] |
08-08 |
04/24/08 |
Revised Borrow and Disposal Site Specifications [*Discontinued*] |
08-05 |
02/11/08 |
Zero Dollar Change Order to Change QC/QA HMA Pay Items to PWL QC/QA [*Discontinued*] |
08-04 |
01/28/08 |
Revised IC-730 Request for Approval of Subcontractor [*Discontinued*] |
08-02 |
12/18/07 |
Unit Price Justification for Extra Work [*Superseded by 17-15 and 17-16*] |
07-28 |
12/17/07 |
HMA Revisions for 2008 [*Discontinued*] |
07-27 |
08/27/07 |
Fabrication and Installation of Worksite Added Penalty Signs [*Discontinued*] |
07-19 |
07/23/07 |
Possession of Roadway Samples [*Discontinued*] |
07-18 |
06/26/07 |
Worksite Added Penalty Signs [*Discontinued*] |
07-14 |
06/12/07 |
House Enrolled Act 1623, Construction Signs [*Discontinued*] |
07-13 |
05/14/07 |
Clarification on Mandrel Testing of Pipes [*Superseded by 09-20*] |
07-10 |
03/26/07 |
IC-730 Request for Approval of Subcontractor [*Superseded by 08-02*] |
07-06 |
01/24/07 |
Monitoring of Suspended or Debarred Firms [*Discontinued*] |
07-03 |
01/24/07 |
Procedures for Determining When the Davis Bacon Act (DBA) Applies [*Superseded by 15-05*] |
07-02 |
12/14/06 |
Lay Rates for Open Graded HMA Mixes [*Discontinued*] |
06-25 |
08/23/06 |
Field Office Internet Service Specification [*Discontinued*] |
06-23 |
08/23/06 |
Policy for Use of Temporary Worksite Speed Limit Assembly Signs [*Discontinued* See Memo 14-06] |
06-22 |
07/17/06 |
Shop Drawing & Falsework Review Procedures [*Superseded by 09-01*] |
06-20 |
06/13/06 |
Change Order & Time Extension Policies [*Superseded by 10-01*] |
06-18 |
04/12/06 |
Documentation That Traffic Control Devices Meet 350 Crash Test Requirements [*Discontinued on 6/5/2015*] |
06-08 |
04/03/06 |
Moisture Tests for HMA & SMA, 2006 [*Discontinued*] |
06-05 |
03/24/06 |
Concrete Mix Designs for 2006 [*Discontinued*] |
06-03 |
01/12/06 |
Contract Items for Cellular Telephones / Radios [*Discontinued*] |
06-01 |
08/24/05 |
Specification Section 306 Milling [*Discontinued*] |
05-13 |
06/13/05 |
Acceptance of Plastic Pipe & Pipe Liner Materials [*Superseded by 12-04*] |
05-11 |
06/24/05 |
05-10 |
|
05/25/05 |
Change Order Procedures [*Superseded by 06-18*] |
05-09 |
04/21/05 |
Memorandum 04-03 QC/QA Failed Materials Policy Revision [*Discontinued*] |
05-07 |
03/29/05 |
Hot Mix Asphalt (HMA) Paver Modifications [*Discontinued*] |
05-06 |
03/29/05 |
Special Provision for MSE Retaining Walls on Active Contracts [*Discontinued*] |
05-04 |
03/05/05 |
Change Orders [*Superseded by 06-18*] |
05-02 |
09/23/04 |
Specification Section 306 Milling [*Superseded by 05-13*] |
04-12 |
06/08/04 |
QC/QA HMA Quality Assurance Adjustments and Failed Material [*Discontinued*] |
04-09 |
05/21/04 |
Use of Prime Coat [*Discontinued*] |
04-08 |
04/23/04 |
Flexible Tubular Marker [*Discontinued*] |
04-07 |
03/22/04 |
Standard Specifications Section 213, Flowable Backfill [*Discontinued*] |
04-04 |
03/30/04 |
QC/QA Failed Materials Policy Revision [*Superseded by 05-07*] |
04-03 |
03/03/04 |
Stockpiling of Steel Products [*Discontinued*] |
04-02 |
02/23/04 |
Materials and Tests Approved Lists [*Discontinued*] |
04-01 |
12/19/03 |
Materials & Tests Approved Lists [*Superseded by 04-01*] |
03-16 |
05/06/03 |
PG Binder Sampling and Testing [*Discontinued*] |
03-06 |
05/05/03 |
Acceptance of Widening Mixtures [*Discontinued*] |
03-05 |
01/29/03 |
Buy American Specification [*Discontinued*] |
03-02 |
07/10/02 |
02-11 |
|
07/02/02 |
Contractor's Acceptance Procedures on HMA Volumetric & SMA Contracts [*Discontinued*] |
02-10 |
06/21/02 |
Revised Change Order Approval Policy [*Superseded by 06-18*] |
02-08 |
05/29/02 |
2002 SMA Specifications [*Discontinued*] |
02-05 |
04/19/02 |
HMA Binder Content Testing Policy [*Discontinued*] |
02-03 |
10/17/01 |
Clarification of Field Office Specification 105.17 [*Discontinued*] |
01-13 |
10/04/01 |
Use of Fly Ash in Concrete after October 15 [*Discontinued*] |
01-11 |
07/11/01 |
Maintenance of Attenuator & Guardrail End Treatments [*Superseded by 18-04*] |
01-08 |
06/25/01 |
Bridge Paint Specification Changes [*Discontinued*] |
01-07 |
05/30/01 |
HMA Binder Content Testing Policy [*Discontinued*] |
01-05 |
04/05/01 |
Clarification of Specification 105.17 (Field Office) [*Discontinued*] |
01-03 |
01/02/01 |
Density & Moisture Controls on HMA Mixtures [*Discontinued*] |
01-01 |
12/14/00 |
Time Extensions [*Superseded by 06-18*] |
00-19 |
10/18/00 |
Worksite Traffic Supervisor [*Discontinued*] |
00-18 |
09/21/00 |
Use of Fly Ash in Concrete after October 15 [*Discontinued*] |
00-17 |
09/05/00 |
Specification Revision for 909.02(e) [*Discontinued*] |
00-16 |
06/20/00 |
Change Order & Time Extension Approval Authority [*Superseded by 06-18*] |
00-13 |
05/24/00 |
Bridge Painting Subcontractors [*Discontinued*] |
00-11 |
03/31/00 |
HMA Notched Wedge Longitudinal Joint [*Discontinued*] |
00-10 |
03/31/00 |
Plate Samples, HMA Thickness Greater than 75 mm [*Discontinued*] |
00-09 |
03/31/00 |
HMA Roller [*Discontinued*] |
00-08 |
03/20/00 |
Random Crack Remediation for Concrete Pavement (PCCP) [*Discontinued*] |
00-07 |
03/06/00 |
Spec 904.02(d) Surface Aggregate Requirements [*Discontinued*] |
00-05 |
03/06/00 |
Spec for Glass Beads & Thermoplastic [*Discontinued*] |
00-04 |
03/01/00 |
HMA Binder Content Policy 2000 [*Discontinued*] |
00-03 |
02/04/00 |
Guidelines for Transportation Enhancement Projects [*Discontinued*] |
00-02 |
08/31/99 |
Field Office Computers - Y2K - [*Discontinued*] |
99-10 |
08/12/99 |
Ignition Oven for HMA Mixture with Dolomite [*Discontinued*] |
99-09 |
05/03/99 |
TD 459, QA Quantity Adjustments [*Discontinued*] |
99-07 |
04/23/99 |
Use of Maturity Meter for PCC Pavement [*Discontinued*] |
99-06 |
04/23/99 |
Details to Standard Drawings for Guardrail Transition, Type TGB [*Discontinued*] |
99-05 |
04/09/99 |
Longitudinal Joints in HMA [*Discontinued*] |
99-04 |
03/30/99 |
Detail Changes to Standard Drawings for Guardrail Transition, Type TGB [*Superseded by 99-05*] |
99-03 |
03/22/99 |
400 Spec Section of the Standard Specification [*Discontinued*] |
99-02 |
03/01/99 |
AE-PL Used as a Prime Coat [*Discontinued*] |
99-01 |